Sludge
Thickening and Dewatering Facility

Value:
$ 40 000 000 plus,
including supplied equipment

Owner:
Regional Municipality of
Ottawa-Carleton

Project Manager:
RPA Consultants

Prime Consultant:
Gore & Storrie Ltd.

Project Description:
The Sludge Thickening and
Dewatering Facility is the central component of the Regional sewage management operation,
called the Robert O. Pickard Environmental Centre, on Shefford Road in Ottawa East.

The equipment included 13 centrifuges, costing $ 1 million each, to be used for
thickening waste activated sludge. In addition, 8 350-h.p. boilers were installed, burning
either natural gas or gas generated from the digesters, to supply both process heat and
central heat for the site.

The building's structure utilized precast and curtain wall construction over
structural steel and reinforced concrete. |
|



Project Exterior - Southwest Elevation
Sludge
Thickening and Dewatering Facility,
Shefford
Road, Ottawa.



Interior - Third-Floor Process Area
Screw
conveyors move Thickened Waste
Activated
Sludge (TWAS)
|